Variance chartActual against plan.
Actual as bars, plan as an outline behind them, and above them the gap itself as small green and red bars.
- Answers How far from plan or average?
- Your data actual and plan per period or item
- Periods about 4 to 24
- Gap actual minus plan
- Excel and Power BI a column chart with a second series
- Actual
- Plan
- Above plan
- Below plan
What is a variance chart?
A variance chart shows actual values against a plan (or budget, or forecast) and draws the difference itself as its own small bars: green above plan, red below. The reader does not need to compare two bars by eye: the gap is already drawn, with its size and sign.
A sales team compares six months of actual sales with the plan. The outlines are the plan, the solid bars are what was sold, and the strip on top shows the gap: February missed by 17, June beat the plan by 23.
Why use a variance chart?
Because the gap to plan is what managers act on.
- The gap is drawn. No need to subtract two bars by eye.
- Sign by colour. Green ahead, red behind.
- Actual stays visible. The size of the business is still there.
- A reporting standard. Finance and controlling teams use it every month.
How does a variance chart work?
Four steps put the plan and the gap beside the actual.
- Step 1 of 4The frameMonths across, sales up, and a strip on top for the gap.
- Actual
- Plan
- Above plan
- Below plan
- Step 2 of 4Actual and planSolid bars for actual, dashed outlines for the plan.
- Actual
- Plan
- Above plan
- Below plan
- Step 3 of 4The gap as barsActual minus plan, as small bars above and below the strip's line.
- Actual
- Plan
- Above plan
- Below plan
- Step 4 of 4The gap as numbersEach gap written on its bar.
- Actual
- Plan
- Above plan
- Below plan
What are the parts of a variance chart?
Four parts, and each one has a job.
- Actual
- Plan
- Above plan
- Below plan
- Actualwhat really happened
- Planthe target, as an outline
- Above plana gap bar going up, in green
- Below plana gap bar going down, in red
How do you read a variance chart?
Three looks, in this order.
- Read the gap stripFour months above plan, two below.
- Actual
- Plan
- Above plan
- Below plan
- Find the biggest missFebruary: 98 against a plan of 115, 17 short.
- Actual
- Plan
- Above plan
- Below plan
- Read the trendThe gap grows at the end: May +12, June +23.
- Actual
- Plan
- Above plan
- Below plan
What kinds of variance chart are there?
The same half year, three ways.
- Kind 1Bars and gapsActual, plan outline and the gap strip.
- Actual
- Plan
- Above plan
- Below plan
- Kind 2Gaps onlyOnly the gap per month, as bars left and right of zero.
- Kind 3Plan as a lineActual as columns, plan as a line on top.
The gap can also be shown in percent of plan, which compares big and small months fairly.
When should you use a variance chart?
When every period or item has a plan, and the gap matters.
- there is a plan, budget or forecast for each value
- the gap drives the decision
- there are about 4 to 24 periods or items
- both size and gap matter
- there is no plan (a column chart)
- only the total gap matters (a KPI card)
- you explain how a total changed step by step (a waterfall chart)
Variance chart or clustered columns?
A drawn gap, or two bars to compare by eye.
- Actual
- Plan
- Actual
- Plan
- Above plan
- Below plan
Clustered columns put actual and plan side by side, and the reader must judge the gap from two bar heights: hard when the gap is small. The variance chart draws the gap itself, so a 4 below plan in April is as easy to see as 23 above in June.
How do you make a variance chart?
Columns with a second series, in Excel or Power BI.
In Excel, draw actual and plan as a clustered column chart with series overlap at 100%, plan with no fill and a dashed border; add a second small chart of =actual-plan with Invert if negative on for the red bars. In Power BI, a column chart of actual with plan as an error bar or target line, plus a measure for the gap (actual against target in DAX, budget variance).
What goes wrong with variance charts?
The most common mistake, and its fix: the wrong sign for costs.
- flip the colours for costs: below plan is green
- say so in the key
| Mistake | Why it hurts | Fix |
|---|---|---|
| Green for over-budget costs | Bad looks good | Colour by good and bad, not plus and minus |
| Gap and actual on one scale | Small gaps vanish | The gap in its own strip |
| No plan shown | Readers cannot judge the target | Plan as an outline or line |
| Absolute gaps for very different sizes | Big months always dominate | Add the gap in percent |
| Too many periods | The strip turns to noise | About 4 to 24 |
Every chart for “How far from plan or average?”
- Against zero or averageDiverging bar chartBars to the left and right of a middle line.
- Against zero or averageSurplus and deficit chartA line filled above and below zero in two colours.
- Survey answersDiverging stacked barAgree to the right, disagree to the left, for survey scales.
- Within limitsControl chartA line with an average and limits, to spot what is unusual.
Read on, step by step.
Does it fit your data? Try it.
Paste your table into Chart Compass, say what the chart should show, and see the charts that fit, drawn with your own numbers. It runs in your browser, so the data stays with you.