Power BI now has a Gantt chart: what the preview does

Since the October 2026 update, Power BI Desktop has a built-in Gantt visual in preview. The fields it needs, how it shows progress and milestones, how to turn it on, and what to keep in mind while it is a preview.

Short answer: yes. The October 2026 Power BI update added a built-in Gantt visual, in preview. Turn it on under Options, Preview features in Power BI Desktop and restart. The only required field is the task label; add Start and End for duration bars, leave End blank for a milestone, and add a percentage measure to show progress on each bar. Tasks group into up to three category levels.

The chart, part by part: What is a Gantt chart? draws its parts and shows how to read one, its kinds and the mistakes to avoid.

Until now, a Gantt chart in Power BI meant an AppSource visual or a stacked bar chart with a hidden first series. A project report had to depend on a third-party visual or a workaround. The new core visual changes that, with one caveat: it is a preview.

Nothing loads from YouTube until you press play. Then Google receives your IP address and may set its own storage. Narrated with an AI-generated voice. Privacy

What does the Gantt visual need?

FieldWhat goes inExample
Task label (required)One row per taskDesign the homepage
StartA date or a measure2026-01-05
EndA date or a measure; blank draws a milestone2026-01-23
ProgressA measure, percentage complete60%
CategoriesUp to three levels to group tasksPlanning, Development, Testing
Columns and tooltipsOwner, status, durationSam, On track, 15 days
The Gantt visual's fields (made-up project)

Start and End can both be measures, which lets you decide how dates roll up to a phase: the earliest start and the latest end, for example.

How do progress and milestones show?

Progress is drawn inside each bar, either as a lighter overlay or as a fill inside an outlined bar; the Format pane sets how much of the bar's height it takes. A milestone is a task with a start date and no end: the visual draws it as a marker on that date. One way to get there is an End measure that returns blank when the task has a milestone flag.

How do you colour and scale it?

Set one colour under Rows, Color and it cascades: bars and milestones in full colour, category backgrounds lighter (70%, 80% and 90% transparent for the three levels). Choose More granular to colour by category or by task. The date axis can auto-scale between years, months and days as you zoom, or show up to two fixed levels, like months over years.

What did the November update add?

The November 2026 update (still preview) adds column totals and row data labels, fixes progress-bar formatting and keyboard navigation, and makes the default columns wider.

  • Totals: Format visual pane, Columns, Totals. Subtotals at a category level only appear for columns that use a measure or an aggregation, so put a duration measure in the column, not a plain text field.
  • Data labels: Format visual pane, Rows, Data labels, to write a value such as the progress or end date on each bar.
  • Per-level styling: select a column and a level to style category subtotals differently from task rows.
TaskCategoryDuration (days)Progress
Scope workshopPlanning5100%
RequirementsPlanning1060%
Budget sign-offPlanning150%
Planning subtotal30
A Planning phase with a Duration (days) column summed by a measure

The subtotal is the measure's sum, 5 + 10 + 15 = 30 days; with a text column it would stay empty. The column area sizes itself to show all columns; set its width and each column's width yourself if you want a scrollbar instead.

The axis can also shade days of the week (weekends, for example), and readers can zoom into a shorter window and back out.

What should you keep in mind while it is a preview?

  • Turn it on first: Options, Preview features, then restart Desktop.
  • Check before you publish: a preview can change before it is final, so test the report in the service before you share it widely.
  • Keep the data simple: one row per task, real dates, and a percentage between 0 and 1 for progress.
  • Stay under 1,000 rows: that is the visual's limit.
  • Formats in tooltips and columns: measure formatting might not show there; set it under Data format on the General tab.

Where can you check this?

Where do you start?

Build the task table first: one row per task with a start, an end and an owner. For other project numbers, see order cycle time. To check which chart fits your data, paste it into Chart Compass.