Gantt chartA plan on a calendar.
One bar per task, from its start to its end, on a calendar. What happens when, what overlaps, and where today falls.
- Answers Where does it go?
- Your data each task's start and length
- Tasks about 4 to 30
- Time days, weeks or months
- Excel and Power BI a stacked bar chart
What is a Gantt chart?
A Gantt chart shows a plan as bars on a time axis: one row per task, each bar running from the task's start to its end. Bars that overlap run at the same time, a diamond marks a milestone (a moment, not a task), and a today line shows where the plan should be now. A darker part of a bar can show how much is done.
A small team plans a new website over ten weeks. It is week 6: design and planning are done, building is under way, and the texts are half written.
Why use a Gantt chart?
Because a plan is about time, and a list of dates hides it.
- When at a glance. Each task sits on the calendar.
- Overlaps show. Tasks that run at once stack above each other.
- Progress shows. The today line and the done part of each bar.
- The project standard. Teams and managers plan with it for a century.
How does a Gantt chart work?
Four steps put tasks on a calendar.
- Step 1 of 4The calendarWeeks across, one row per task.
- Step 2 of 4A bar per taskFrom its start to its end; a milestone is a diamond.
- Step 3 of 4Mark todayA line at week 6: tasks to its left should be done.
- Step 4 of 4Show progressThe darker part of a bar is the share done.
What are the parts of a Gantt chart?
Four parts, and each one has a job.
- Taska bar from start to end
- Milestonea moment, drawn as a diamond
- Todaywhere the plan should be now
- Time axisdays, weeks or months
How do you read a Gantt chart?
Three looks, in this order.
- Find the endThe launch is planned for week 10.
- Look at the today lineTexts and building run now, both under way.
- Check what waitsTesting starts in week 8, so building must be done by then.
What kinds of Gantt chart are there?
The same plan, three ways.
- Kind 1With progressToday line and the share done of each task.
- Kind 2One colourCalm, for a plan without a story.
- Kind 3Critical path litThe chain of tasks that sets the end date.
Project tools add dependencies (lines from one task to the one that waits for it) and baselines (the first plan as a thin bar under the current one).
When should you use a Gantt chart?
When a plan has tasks with dates, and timing matters.
- tasks have a start and an end
- overlaps and order matter
- you track progress against dates
- there are about 4 to 30 tasks
- the order matters but not the dates (a flowchart)
- you show events, not tasks (a timeline)
- there are hundreds of tasks (group them into phases first)
Gantt chart or a task list?
Bars on a calendar, or dates in columns.
- start and end dates in columns
- exact, but overlaps and gaps must be worked out date by date
A task list is the source: exact dates and owners. The Gantt chart draws the same dates, so the reader sees that texts and building overlap and that testing waits for building.
How do you make a Gantt chart?
A stacked bar chart with a hidden first part.
In Excel, put each task's start and length in two columns, draw a stacked bar chart, give the start part no fill and reverse the task order on the axis. Project tools draw it from a task list. In Power BI, a Gantt custom visual from AppSource takes the task, start and end (custom visuals in Power BI).
What goes wrong with Gantt charts?
The most common mistake, and its fix: a plan nobody updates.
- drawn at the start and never changed
- the bars say "on time" while the work is late
| Mistake | Why it hurts | Fix |
|---|---|---|
| No today line | Nobody sees what is late | Mark today |
| Never updated | The chart lies | Update progress every week |
| Too many tasks | A wall of bars | Group into phases |
| No milestones | Key dates hide | Diamonds for launches and deadlines |
| Tasks in random order | Hard to follow | Order by start date |
Every chart for “Where does it go?”
- Flows between groupsSankey diagramBands from one group to the next, as wide as the amount that moves.
- Flows between groupsAlluvial diagramHow groups change across several stages, as flowing bands.
- Flows between groupsChord diagramFlows between items around a circle.
- StepsFunnel chartBars that shrink step by step, for how many make it through.
- StepsFlowchartBoxes and lines for the steps and choices in a process.
Read on, step by step.
Does it fit your data? Try it.
Paste your table into Chart Compass, say what the chart should show, and see the charts that fit, drawn with your own numbers. It runs in your browser, so the data stays with you.